Day 36 – Plumber installed soil pipe
The plumber came and put the pipes and soil pipe in the new en-suite. En-suite area Image 1 of 9
The plumber came and put the pipes and soil pipe in the new en-suite. En-suite area Image 1 of 9
I finished laying all my cat6 and AV cables in the loft. Installing Cat6 Cables Image 1 of 1
I started to lay all my cat6 and AV cables in the loft. Installing Cat6 Cables Image 1 of 1
First fix electrical done and the removal of the cupboards downstairs. p1090209 Image 1 of 11
I have been away with work for the past few days so have not been able to keep a daily update for the past few evenings. There was a lot done when I was away…
Some more floor boards went in today as well as the area for the staircase had been cleared in the loft. more floor boards Image 1 of 5
The structure of the dormer is now full in place and the original roof below it has now been removed. You can really see how much space is in there now and can visualise the…
The dormer continues to take shape, it now has a full wooden shell, a lot of the original roof still remains underneath. Inside the Dormer Image 1 of 5
The dormer has started to take shape today with the new roof and support beams in place. The large majority of my roof tiles are still in place and sections have just been removed to…
The roof started to come down today to make space for the dormer. They have started to take the first two or three rows of roof tiles away starting from the top as well as…