Day 4 – Plumbing
The plumber was in today installing a new Worcester Bosch boiler in the kitchen and moving the water pipes in the loft further to one side so they will be in the void space rather…
The plumber was in today installing a new Worcester Bosch boiler in the kitchen and moving the water pipes in the loft further to one side so they will be in the void space rather…
Quite a bit of progress had been made today; I came home to find the large steel beam had been put in at the back of the house which will be used to take the…
The weather was quite bad today to so it made it awkward to move materials to the skip, but it was more than half filled by the end of the day. The day was spent…
The first day of work today, Steve turned up promptly at the time we agreed and protected the carpets in the hallway and underneath the loft hatch before he started to rip out all the…
When I was in work today the first batch of materials were delivered. It mainly consisted of the steel beams, plenty of wood of various sizes, a lintel to go over one of the windows,…